Sunbury Ohio Data Center Vote: What Nov. 3 Means for Buyers

"As the property owner, AWS may develop and use its property in accordance with the regulations of the City of Sunbury's Limited Industrial ('LI') zoning district."

That sentence comes from the City of Sunbury's own data center FAQ, dated February 24, 2026. The FAQ was answering a resident question: is there anything I can do to stop it? The city answered that a data center is a permitted use in that district. It added that the land was rezoned on May 29, 2024, through Ordinance No. 2024.11, after two public hearings and five public meetings.

On Nov. 3, Sunbury voters will decide whether to add a data center ban to the city charter. Lawn signs and headlines treat it as a yes-or-no vote on Amazon. If you're comparing Sunbury with Galena, Delaware or Westerville this fall, the more useful point is that the vote doesn't close the question on election night. The Amazon project depends on several separate approvals, and most of them were still open in the latest public reporting.

The Order Things Happened In

The vote makes more sense against the full sequence. Here is what the public record shows:

  1. May 29, 2024. City Council rezones the land to Limited Industrial, where data centers are permitted.
  2. November 21, 2024. The city announces that Amazon Data Services, Inc. plans a "megaproject" data center campus in the Sunbury Business and Technology Park.
  3. April 2026. Council unanimously adopts a temporary moratorium on data center development through Jan. 31, 2027.
  4. May 27, 2026. Gov. Mike DeWine pauses consideration of new state data center tax exemption requests.
  5. July 15, 2026. Council sends a citizen-led charter amendment to the ballot.
  6. Oct. 22, 2026. The city's next special meeting on data centers, covering industrial noise and Ohio EPA air-quality guidance.
  7. Nov. 3, 2026. Election Day.
  8. Jan. 31, 2027. The moratorium is set to expire.

The zoning was settled two and a half years before the ballot. Since then the open questions have been about power, water, a development agreement and now the charter. The moratorium also runs almost three months past the election.

What the Ballot Actually Says

On the Delaware County sample ballot, the measure appears as a proposed amendment adding Article XI, Section 11.05, "Prohibition of Construction of a Data Center." The Delaware Gazette printed the full text, and three parts of it matter here.

  • The threshold. The ban covers facilities with an aggregate monthly demand or peak load above 25 megawatts. That load can be added up across contiguous or aggregated parcels.
  • The definition of construction. It covers buildings, infrastructure, facilities and the "preparations and modifications" for them.
  • The final clause. It says, "This Section is self-executing."

Based on the text the Gazette published, the amendment doesn't carve out parcels that were already zoned. In the coverage reviewed for this post, no city official or attorney has said publicly whether a charter provision adopted in 2026 would apply to land that got its permitted use in 2024. That question will likely be answered after the vote, not on the ballot.

The measure came from residents, not City Hall. Delaware Source reported that the local group Big Walnut for Responsible Growth led the petition and that the Board of Elections certified 351 valid signatures, more than double the 172 required. The same report said Council's unanimous vote only certified the measure for the ballot and did not amend the charter itself. The 25-megawatt language is modeled on a statewide amendment that Conserve Ohio hopes to put before voters in 2027.

The Approvals That Don't Depend on the Vote

The vote is one gate. The rest of the project has its own, and as of the latest public reporting, several hadn't been cleared.

According to Delaware Source's May 7 report, the final site plan hadn't been submitted and utility planning was still underway. The city's February FAQ said construction depends on a development agreement covering public infrastructure, plus power and water from regional providers. The infrastructure list in that FAQ includes a new sanitary pump station, sewer and water line extensions, a new water tank and at least one new road. No later public source confirms that any of these steps has been completed.

Water may be the slowest step. At the city's June 25 forum, Delaware Source reported that Del-Co Water COO Brian Coghlan called serving a hyperscale data center "a challenge." He recommended a water user agreement that could take 12 to 24 months to reach. The same report said the project would use an estimated 7% to 8% of Del-Co's system capacity. That would make it the utility's largest customer by far. The current largest is the Columbus Zoo and Aquarium, at about 1% of total usage. Coghlan also said households would get priority over the data center during a drought.

Power is a question of scale. Energy consultant John Seryak estimated the facility could need 100 to 300 megawatts, compared with about 10 megawatts for the entire city of Sunbury today. He also explained that transmission connection costs are shared across the AEP Transmission footprint, which covers Ohio and parts of 11 other states. Sunbury households wouldn't carry those costs alone, but they could see transmission-related charges the same way they could from data centers anywhere else in that territory.

What the City Offered, and What Residents Raised

The city's case for the project is laid out in the FAQ. Sunbury offered a Community Reinvestment Area property tax exemption of 87.5% for 15 years and 75% for another 15 years. In return, AWS committed to at least $2 billion in capital investment, at least 50 full-time jobs averaging $90,000 a year, and 30 years of operation at the site. The FAQ says AWS also looked at sites in Indiana, Virginia and Minnesota, and that the incentive was a major factor in its choice.

At the April 15 council meeting, resident comments covered noise, light, property values, health and environmental effects, electric and water capacity, farmland, community character, incentives and transparency. The minutes describe overall sentiment as strongly opposed. Council adopted the moratorium at that same meeting. The coverage reviewed for this post didn't identify an organized campaign urging a "no" vote.

The city's FAQ describes the Business and Technology Park as more than 1,300 acres east of Sunbury, between State Route 37 and Vans Valley Road. Public sources don't give an exact boundary for the AWS parcel, so a buyer can't measure the distance from a given street to a building footprint yet.

The Housing Market Sitting Beside All This

This is where the timeline matters for buyers. The data center question will likely stay open into 2027. Meanwhile the Sunbury resale market is thin.

The Columbus REALTORS® Local Market Update for Sunbury (Corp.), current as of September 9, 2026, shows these August 2026 figures:

Metric, August 2025 2026
Median sales price $499,000 $502,450
Homes for sale 34 19
Months supply 2.9 1.3
Days on market until sale 55 32
New listings 20 8
Closed sales 9 24

Prices barely moved year over year. Supply shrank. Eight new listings in a month gives buyers few homes to compare, and the year-to-date median through August was $499,900. The report also notes that these figures don't account for seller concessions, and small monthly samples can make percentage changes look extreme.

New construction is filling some of the gap, but most of it isn't detached homes. 1808Delaware's summary of the city's July zoning report counts 354 residential units in development during 2026, and 294 of them are multifamily. Here is where the larger projects stood in that report: Kintner Crossing had zoning certificates for 39 of 188 units, Woodland Lake for 274 of 451, and Eagle Creek for 108 of 232, with 87 cleared for occupancy. Price Ponds was 69% permitted for construction. Eagle Creek Highlands, planned at 239 units, hadn't issued any certificates yet. Pulte advertises Price Ponds homes from $444,990. Through July, Sunbury had issued 93 new-build permits, ahead of 2025's pace of 84 but below the roughly 100-plus of 2023 and 2024.

So a Sunbury buyer this fall is working with few resale choices, a pipeline weighted toward multifamily units such as the walk-up apartments at Woodland Lake, and a major land-use question that probably won't be settled until after the Jan. 31 moratorium expiration at the earliest. None of the sources here predicts what the vote or the project will do to home values, and this post doesn't either. What a buyer can do is find out which approvals have actually been granted and which are still pending. The Oct. 22 meeting, the election result, any filed site plan, a Del-Co water agreement and the moratorium's end date are all public checkpoints.

This post explains how zoning and charter amendments work in general terms. It isn't legal advice, so questions about how a specific rule applies to a specific property belong with an Ohio real estate attorney.

If you're weighing a Sunbury home against the data center timeline, I'll pull the current listings and closed sales, check the latest council and planning records, and go through the dates with you before you make an offer. Sharon Staub. Let's Connect.

Let’s Get Started

With decades of local experience, every client receives knowledgeable guidance, personalized service, and unwavering support throughout the buying or selling process. The focus is on making every transaction smooth, successful, and stress-free.

Follow Me on Instagram