Gahanna Creekside Events for Fall 2026: Plans and Rebuild Updates

"The City anticipates the required elements related to the flood mitigation to begin in the fall of 2026." That sentence is still posted in the City of Gahanna's Creekside FAQ, and it is the reason anyone who parks under the plaza or walks the trail along Big Walnut Creek might expect fences by now.

It's October 5, and the city's bid posting for that work still lists its status as "Open" and its closing date as "Open Until Contracted." The construction manager who would sequence the work hasn't been signed. Until that happens, nobody can say when the plaza will change. So this fall and holiday season at Creekside will happen on the plaza as it stands today.

Where the Contract Actually Stands

The paper trail is short. Taken in order, it shows the schedule slipping.

  1. May 8, 2026. The city released Request for Proposal 2026-1, seeking a construction manager at risk for "Flood Mitigation & Plaza Improvements of Creekside." Responses were due June 12.
  2. June 1, 2026. In a written Q&A addendum, the city said it expected to go "right into contract negotiations after interview on the week of June 22," that negotiation length was unknown, that City Council still had to approve the contract, and that "Best case scenario would be an August start date."
  3. Same addendum. The city estimated "an approximate 24-30 month construction schedule."
  4. October 5, 2026. Tonight's City Council agenda lists the capital improvement plan ordinance for introduction. It does not list a Creekside construction contract.

August was the best case, and it has come and gone without a contract. The FAQ also says a full funding strategy would go to Council "in the early part of 2026," and that line hasn't been updated either. None of this means the project is stalled. Public works of this size often run late on paper before anyone breaks ground. It does mean the FAQ's "fall of 2026" is a forecast, and the bid page shows the real status.

What the Rebuild Will Change When It Comes

A 24-to-30-month window is long, so it helps to know what will actually be under construction. The bid posting splits the project into five areas: public and private flood mitigation, trail improvements, the upper plaza, the lower plaza and the streetscape. Flood mitigation of the parking structure under the plaza "will be performed at the same time" as the other work.

The preliminary plaza design, as the city describes it:

  • The main event space moves from the back of the property down to the lower lagoon. A central stair links it to the upper plaza.
  • The lower lagoon gets smaller and becomes an amphitheater "to host reimagined community events."
  • An interactive water feature, better lighting and more shade.
  • About 13,000 square feet of connected programming space, plus private patio seating and a secondary plaza between Buildings B and C.
  • The lower trail is reconfigured to connect better with Big Walnut Creek and the trail system west of the plaza, with improved ADA access throughout.

Two practical answers are already on record. The Creekside parking garage stays open for residents and visitors during construction. Flood work inside it will affect "only smaller areas" of the structure at a time. As for which events will be disrupted, the city says that question waits on the schedule: "Once the construction schedule and logistics are determined we will have a better understanding of which events will be impacted." The city also says it's studying how construction would affect businesses on the plaza and along Mill Street, and that it will tell businesses and the public how customers can reach them during the work.

There's no schedule yet, so there's no list of affected events yet. That's why this fall's calendar looks the way it does.

The Plaza's Calendar Through December

With no contractor on site, the district's fall programming is running as usual. Here's what is posted between now and early December:

Saturday, October 17, noon. "Sip & Spells: Sacred Self-Care" at the Ohio Herb Center, 110 Mill St.

Saturday, October 17, 6:30 p.m. "Ghosts of Gahanna," a program on local history and lore, also at the Ohio Herb Center.

Saturday, October 31, 10:30 a.m. "Sacred Smoke," an herb and incense workshop at the Ohio Herb Center.

Friday, November 13, 7 p.m. Next Stop Comedy at Nostalgia Brewing on Mill Street.

Sunday, November 22, 3 to 6:30 p.m. The Holiday Lights Celebration at Creekside Plaza, 117 Mill St. Visit Gahanna lists free family activities, Santa lighting the tree and fireworks, followed by a Creekside Park display of more than 300,000 lights. The listing doesn't say how long the display stays up.

Saturday, December 5, noon to 2 p.m. The Victorian Christmas Celebration at the Gahanna Historical Settlement, 101 S. High St., a short walk from the plaza.

The Ohio Herb Center also runs a virtual Tea Society on October 8, November 12 and December 10 at 7 p.m. That one is online, so it's off the Mill Street map. Event listings change, so check the date the week of anything you plan around.

Holiday Lights matters most here. It happens on the plaza and in the park that the rebuild will eventually redesign, and its programming is exactly the kind the new amphitheater is meant to "reimagine." This year it's scheduled in the space as it stands now.

Mill Street's Empty Lots Are on a Separate Timeline

The cleared ground along Mill Street is easy to mistake for the start of the plaza rebuild. It isn't part of it. In November 2025, City Council approved a development agreement with Connect Realty, Benson Capital and the Gahanna CIC for a private mixed-use project the city describes as about $100 million in private investment. CityScene has described the plan as a mix of housing, businesses, restaurants, a boutique hotel and parking. One city FAQ calls the developer "Connect Real Estate" rather than Connect Realty.

The city's June newsletter said crews were finishing the last demolition there, removing foundations and pavement, and that the sites would be seeded with grass and maintained "until the next phase of development moves forward." The newsletter also said detailed plans had not been submitted to the city, and that more planning, design and public review would come before construction could start. The project still hadn't reached the Planning Commission by fall. Neither the September 9 nor the October 14 agenda lists it.

So two projects sit side by side here. Each has its own approvals and its own timeline, and neither has a construction date that can be confirmed.

The One Opening Announced for Mill Street

The only new business publicly tied to Creekside this season is Micheli's Osteria + Wine Bar. 614NOW reported on August 25 that the casual, Florence-inspired Italian restaurant planned to open at 101 Mill St. "later this fall." Before opening, it served roasted porchetta focaccia sandwiches at Taste of Gahanna with the Gahanna Chamber of Commerce, where it ran out of food. It also appeared at the Creekside Blues and Jazz Fest. Its food and wine menus were still being finalized at the time. No opening date or posted hours have surfaced since that report.

Micheli's joins a district directory that Visit Gahanna lists as including Barrel & Boar Creekside, Cafe Creekside, Cold Stone Creamery, Marlow's Cheesesteaks, Nostalgia Brewing, Signatures Mill Stone Tavern, Upper Cup Gahanna and Xochilt Mexican Cuisine, among others. Any business opening at Creekside right now is betting on a plaza that will spend about two years under construction once a contract is signed. The city has said it will tell the public how customers can reach businesses during that work.

The Vote That Starts the Clock

For anyone who wants to know when Creekside will change, the thing to watch is the City Council agenda. The city's own Q&A says the construction manager contract needs Council approval. After that, the preconstruction phase is where the city says "construction logistics, coordination, and communication" will be worked out. The event-impact list the FAQ keeps deferring would come out of that phase too. You can follow the RFP's status on the city's bid posting and read the design and parking answers on the Creekside FAQ. Until the bid page shows a contract and Council approves it, the November 22 tree lighting is scheduled on the plaza as it stands today.

Owning a home near Creekside means that two separate projects, plus a construction stretch the city estimates at two years or more, may matter when you plan a sale or compare streets in Olde Gahanna. Sharon Staub has worked in Central Ohio real estate since 1991. She can show you how projects like this tend to show up in pricing and timing, so your plans are based on what has actually been approved. Let's Connect.